Crane and Sling
•	
A crane can be used to lift panels into their final fixing position
•	
Care must be taken to correctly align the sling to the marked 
lifting points (as per attached tables)
•	
Set the packs onto the site in the proper orientation for the 
erection sequence
•	
A spreader bar must be used to ensure that the load is evenly 
disturbed
•	
A spreader bar must be used to ensure that the lifting straps 
do not squeeze in on the panels causing any deformation to 
the panel’s edges and delamination of the skins.
•	
Protective blocks are to be used under the slings to ensure 
that the steel skins are not deformed or crushed during the 
lifting process.
Packs over 1800 kgs and less than 10 meters 
may be lifted as shown in figure
Packs over 1800 kgs and/or over 10 metres 
may be lifted as shown in figure 
8. HANDLING OF THE PANELS